Chennai Metro expedites construction work on Purple Line under Phase-IIRepresentational image

CHENNAI (Metro Rail News): Chennai Metro Rail Limited (CMRL) announced that they have made significant progress on the Phase-II project with the completion of Pilling and U-Gider casting along the Old Mahabalipuram Road (OMR) of the Corridor-3 (Purple Line). The work was carried out by Larsen & Toubro. The work was executed along 10 stations of the corridor connecting Nehru Nagar with Sholinganallur (see Map). 

According to officials, the team successfully executed the completion of 100% piling works amounting to 3,066 piles between Nehru Nagar and Sholinganallur along the OMR. Moreover, they also executed the structural casting by completing all 582 precast prestressed U-shapped girders.

Chennai Metro Phase-2 Project Achieves Major Milestone: 100% Piling and U-Girder Casting Completed for OMR Stretch Corridor-3

​Chennai Metro Rail Limited has reached two major construction milestones on Corridor-3 (Madhavaram – SIPCOT) under Phase-2 Project Contract Package… pic.twitter.com/0JIjcew7jV

— Chennai Metro Rail (@cmrlofficial) July 16, 2026

The pilling work along the busy routes required traffic navigating which was critical along the Thoraipakkam and Sholinganallur junction where the requirement was to integrate two metro stations through flyovers while managing the uninterrupted traffic flow in the route.

CMRL awarded the contract to Larson and Tourbo in May, 2022 to construct the elevated viaduct between Nehru Nagar and Sholinganallur. The corridor is expected to improve connectivity along the Eastern region of the city. 

The weekly brief metro & rail professionals read.

Chennai Metro Phase-II

The Phase-II of Chennai Metro is projected to add 118.9 km to the network with 128 stations. Three corridors are planned to improve the connectivity in the city. The Corridor-3 (Purple Line) covers Madhavaram to SIPCOT, Corridor-4 (Yellow Line) stretches from Lighthouse to Poonamalle Bypass and the Corridor-5 (Red Line) from Madhavaram to Sholinganallur. The project is expected to be completed by the end of 2028.

Also Read: Indian Railways introduces world’s longest Hydrogen Train

Guide
Chennai Metro: the complete guideAll corridors, status, routes and the latest news in one place →

Схожие новости

#Наименование новостиТональностьИнформативностьДата публикации
1 Comment on Bengaluru Metro to connect Tamil Nadu Border: BMRCL plans 9 new stations  by Satish 013.6717-08-2026
2 Comment on DMRC floats electrical tender for Rithala-Kundli Corridor (Phase IV) by davinder singh 015.2618-07-2026
3 Comment on Kolkata Metro Orange Line clears 6 year Chingrighata delay by Junaid 09.3717-08-2026
4Вопрос о строительстве второй ветки метро в Екатеринбурге могут внести в опрос жителей0021-06-2019
5 Comment on Bengaluru Suburban Rail: Double Decker Flyover to approach space limitation  by STANITE U V 07.1319-07-2026
6Shashi Tharoor urges Kerala CM for metro in Thiruvananthapuram017.9416-07-2026
7Сроки строительства четвертой и шестой линий метро Петербурга перенесли на конец 2024 года0009-02-2021
8Реконструкция Лиговского путепровода в Петербурге завершится в сентябре0018-08-2021
9Собянин осмотрел ход реконструкции наземного участка Филевской линии метро0027-08-2019
10Why Trump Is Obsessed with Passing the SAVE America Act08.0128-07-2026

Классификация: Мнения. Схожих патентов: 0. Схожих новостей: 10. Тональность: 0. Информативность: 12.49. Источник: www.metrorailnews.in.